Executive

 

Thursday, 14 October 2021

 

Decisions

 

Set out below is a summary of the decisions taken at the Executive meeting held on Thursday, 14 October 2021.  The wording used does not necessarily reflect the actual wording that will appear in the minutes.

 

Members are reminded that, should they wish to call in a decision, notice must be given to Democracy Support Group no later than 4pm on the second working day after this meeting.

 

If you have any queries about any matters referred to in this decision sheet please contact FionaYoung.

 

<AI1>

4.               Housing Delivery Programme Update

 

Resolved:  (i)      That approval be given to submit a planning application to deliver new homes, community and flexible commercial spaces at the Ordnance Lane and Hospital Fields Road site.

 

                   (ii)      That it be noted that an outline business case has been developed and that this will be refined and brought before Executive post planning permission, to allocate a construction development budget to the project, transfer the general fund part of the site into the HRA through appropriation, and agree the procurement of a construction partner.

 

                   (iii)     That the grant offer of £2.64m under the Brownfield Land Release Fund be accepted to support projects at Ordnance Lane, the former Tang Hall Library site, and Chaloners Road Garage Court, and that approval be given to:

·        use up to £700k of this allocation for the Ordnance Lane project to undertake utility works on site and prepare a tender pack to procure a contractor to undertake enabling works; and

·        put the enabling works contract out to the market, with the contract signed after the business case for the whole site redevelopment has been approved by Executive.

 

                   (iii)     That an additional £500k be allocated from the Housing Delivery Programme capital budget in order to undertake detailed design work at the Ordnance Lane and Hospital Fields Road site in conjunction with the submission of the planning application and completion of the financial business case for this site.

 

                   (iv)    That a grant application be submitted to Homes England to support the delivery of additional Shared Ownership affordable homes on the Ordnance Lane and Hospital Fields Road site.

 

                   (v)     That the lessons learned on Phase 2 projects within the programme, and the progress and approach to projects which may form part of Phase 3 of the programme, including continuing use of the high standards defined in the ‘Building Better Places’ design manual as the set of objectives for the Housing Delivery Programme, be noted.

 

                   (v)     That the progress made on bringing forward proposals for the community-led redevelopment of the former Tang Hall Library and the Morrell House site for housing be noted, and that approval be given to dispose of the former Tang Hall Library and Morrell House sites on long leases for the purpose of enabling construction/delivery of community housing, on condition that any such disposal is made at or above its open market valuation and is subject to a deliverable business case provided from community housing organisations.

 

                   (vi)    That authority be delegated to the Director of Housing, Economy & Regeneration (in consultation with the Chief Finance Officer, Executive Member for Housing, Executive Member for Finance & Performance and the Director of Governance or her delegated officers) to take such steps as are necessary to negotiate and complete the disposal of the sites.

 

Reason:     To progress with the construction, rental and sale of much needed new homes in York set within healthy and sustainable neighbourhoods.

 

</AI1>

<AI2>

5.               School Capital Works at Millthorpe and Manor Schools to Accommodate the Expected Demand for Pupils Places from within the Schools' Catchment Area by September 2022

 

Resolved:  (i)      That, in respect of Millthorpe School, Option 3 be approved, and that £1.9m be allocated by grant agreement from the Basic Needs Fund to South Bank Academy Trust for capital works to create additional teaching and circulation space at the school.

 

                   (ii)      That authority be delegated to the Assistant Director, Education and Skills in consultation with the Director of Governance (or her delegated officers) to take such steps as are necessary to enter into the resulting grant agreement.

 

Reason:     to create the space needed to fulfil the expected demand for a temporary 3-year bulge of pupil places from within the catchment area of Millthorpe School by September 2022.

 

                   (iii)     That, in respect of Manor CE Academy, Option 3 be approved and that funding of £1.1m from the Basic Needs fund (with a proportion to be recouped from S106 monies in relation to the Civil Service housing development) for capital works to the Academy by grant agreement to Hope Sentamu Learning Trust.

 

(iv)    That authority be delegated to the Assistant Director, Education and Skills in consultation with the Director of Governance (or her delegated officers) to take such steps as are necessary to enter into the resulting agreement.

 

Reason:     To create the space needed to fulfil the expected demand for a temporary 3-year bulge of pupil places in the SPA West area (excluding the Millthorpe catchment area) by September 2022.

 

</AI2>

<AI3>

6.               Highways Infrastructure Asset Management Plan

 

Resolved:  That the introduction of a highways management framework, including implementation of the Highways Infrastructure Asset Management Plan and theHighways Safety Inspection Manual, be approved, subject to the addition of the words ‘and ward councillors’ to the end of section 2.3.3(b) of the Manual.

 

Reason:     To ensure delivery of all highway maintenance services in an efficient and cost effective manner.

 

</AI3>

<TRAILER_SECTION>

</TRAILER_SECTION>

 

<LAYOUT_SECTION>

 

FIELD_SUMMARY

 

</LAYOUT_SECTION>

<TITLE_ONLY_LAYOUT_SECTION>

 

</TITLE_ONLY_LAYOUT_SECTION>

<HEADING_LAYOUT_SECTION>

FIELD_TITLE

 

</HEADING_LAYOUT_SECTION>

<TITLED_COMMENT_LAYOUT_SECTION>

FIELD_TITLE

 

 

</TITLED_COMMENT_LAYOUT_SECTION>

<COMMENT_LAYOUT_SECTION>

FIELD_SUMMARY

 

</ COMMENT_LAYOUT_SECTION>

 

<SUBNUMBER_LAYOUT_SECTION>

 

FIELD_SUMMARY

</SUBNUMBER_LAYOUT_SECTION>

 

<TITLE_ONLY_SUBNUMBER_LAYOUT_SECTION>

 

</TITLE_ONLY_SUBNUMBER_LAYOUT_SECTION>